 |
The sewerage load has increased to three times the
designed load to 30 MLD and the sewers a re totally inadequate to
carry this flow. The sewers are running full and hence the thickness
of the sewerage at top is nearly reduced to 30%. Moreover the roadside
open drains are also connected to the sewers hence causing the storm
water to flow through the sewers, which is far beyond the capacity. As
a result the sewers are leaking and the surrounding areas get water
logged due to the insufficient drainage/ drying capacity.
Existing open drains along the road are joined to
the existing sewerage system thereby damaging the main sewers by
clogging choking and overflowing. The intermingled sewer lines and the
drainage lines are emptied into the Godavari River thus polluting the
River. Approach for maintenance& repairs are difficult as the lines
are covered by permanent structure.
Area North of Railway Line
The development in the area is new and better
planned with proper roads, educational institutes etc. However only 30
% of the area is covered under the sewerage scheme as the main sewers
and street lines are not laid yet. Moreover the sewers are leading to
the south area where the sewers cannot carry their load.
The existing houses (70% of the total) are
connected to temporary arrangements i.e. septic tanks. It will be
necessary to design a new system for 70% of the balance area. The
sewerage shall be collected near Data Mandir and directly pumped to
the sewerage treatment plant.
Villages under the NWMC:
The villages merged with the NWMC recently do not have the proper
infrastructure facilities available. Each village area will have to be
studied and provision of an under ground sewerage system or individual
septic tanks can be analyzed.
General:
The sewer lines in the area south of Nanded are old and are
running to its fullest capacity. The sewers are not accessible at many
areas where structures are constructed over the sewer lines. The north
area requires new network.
Proposed Developments in the Sewerage and
Sanitation Sector
• The entire sewerage system requires to be
studied properly in light with the increased population and sewerage
load and anticipated growth in future.
• The existing sewers laid in the south area will not be replaced due to
site conditions. Since the street lines in these areas are in working
condition, only main sewer lines shall be designed and laid
separately.
• The open drains by the roadside shall be properly built and joined to a
new storm water drain to isolate sewerage system.
• North area sewerage scheme shall be implemented. But the sewerage
selection from the north section shall be segregated from the south
and pumped separately to sewerage treatment plants.
• Gurdwara Area requires resurvey of the system and augment the same by
laying additional sewer line, constructing manholes/chambers and
constructing the new storm water drainage system
• Temporary sewage disposal system shall be designed and implemented at
the temporary accommodation camps.
• The drains leading to the river shall be trained suitably through box
type permanent R.C drains along the river course to avoid pollution.
• Mobile toilet vans shall be provided at all the major camps.
• Sulabh Sauchalays for pilgrims shall be constructed at all the camps and
city locations.
Sector Focus
The main developments in the sector could be concised as:
• Laying of new sewers in South portion of
Nanded
• Laying of new sewer mains and in north portion of Nanded
• New underground sewerage system have to be planned for new villages in
NWMC
• Storm water drains of the city will be rebuilt for training properly
towards the river.
• Treatment of the open drainage to avoid the contamination of the river
water.
• Additional sewerage treatment plant will be constructed.
Cost work out for the underground system Sewer Line Costing
A. Development Particulars for Sewer Lines
• Total Length of Underground Sewer Lines
: 60 Kms
• Hume Pipes NP 3 class- Starting with 300 d and ending with 900 d
• Average Diameter of Pipe
: 600 mm dia
• Unit Cost
: Rs. 1800/mtr
• Average depth of excavation
: 4. 0 mtr
• Manholes @ of 30 mtrs with a unit cost of Rs.10, 000/ MH
Gurudwara Development
|
Item
No |
Description |
No |
L |
B |
D |
Unit
Rate (Rs) |
Cost |
|
1 |
Excavation |
|
1000 |
1.20 |
4 |
115 |
5,52,000 |
|
2 |
Hume
Pipes |
|
1000 |
|
|
1,800 |
1800000 |
|
3. |
Manholes |
30 |
|
|
|
10000 |
300000 |
B. Cost of Sewer Line for 1 Km
: Rs. 26, 52, 000
Pumping Infrastructure Costing
A. Development Particulars for Pumping Infrastructure
• Four New Pumping stations
• 2 No of 150 HP, 60HP & 40 HP Pumps to be installed
• Total Pump Capacity of 500 HP / Pump Room
|
Item No |
Description |
No |
Unit Rate (Rs) |
Cost |
|
1 |
Pump Rooms (Civil
Cost) |
4 |
15,00,000 |
60,00,000 |
|
2 |
Pumps 500 HPX 4 |
6 |
3000/HP |
80,00,000 |
B. Cost of Pumping Infrastructure
: 1,40,00,000
Sewerage Treatment Plant Costing
A. Development Particulars for the STP
• Design of the STP would be for 9 Lac Souls
• Consumption of water would be 100 lpcd .
• Discharge has been assumed to be 90 % of the total Consumption
• People/ Household : 4.5
• No of household : 200,000
• Cost of Connection/ House : Rs.1000
B. Cost Summary for the Sewerage Treatment
• Cost of STP
: 30,00,00,000
• Cost of Connection
: 20,00,00,000
• Cost for Sewerage Layouts : 15,91,20,000
• Pumping Stations
: 5,60,00000
Cost Summary : 71, 51,00,000
Add 20% Contingency : 14, 30,20,000
Total Cost Estimate for the Sewerage System: 85,
81, 20, 000 ~ 86 crores
COST WORKOUT FOR THE STORM WATER DRAINAGE
Cost Summary
Estimation for 1M running length
• Excavation
:Rs.48.30
• P.C.C M10
:Rs. 328.90
• RR Masonry :Rs.
254
• Coping M15 :Rs.
107.80
• Pointing
:Rs.25
Total
:Rs. 764.30
For 1 Km Length : Rs. 7, 70,000
|
 |